Last Updated: December 04 2023
How to Use Project Overview Materials in Jobs
Overview
Use the Materials tab to track all materials required for the project, as well as compare required materials and materials actually used. The Materials and Resources tabs can be used together to effectively track parts and labour. Learn more about tracking labour in How to Use Project Overview Resources.
The Materials tab is one of the reporting tools in the Project Overview. Learn more in How to Use the Project Overview in Jobs.
In order to view content or perform actions referred to in this article you need to have the appropriate permissions enabled in your security group. Go to System > Setup > Security Groups and access your security group to update your permissions. The relevant security group tab and specific permissions for this article can be found here:
Materials | Each item associated with the project listed by section and then by cost centre. |
Required Quoted | The quantity of items added in the Parts & Labour tab. |
Required Additional | If the project was locked with budget and prices, additional items that were added after the project was locked. |
Required Total | The sum of the Required Quoted and Required Additional columns. |
Actuals Assigned | The quantity of items assigned to the project. |
Actuals Back Order | The quantity of items ordered to the project but not yet receipted. |
Actuals Total |
The sum of the Actuals Assigned and Actuals Back Order columns. Values display in red if the amount assigned is less than the total required quantity. Values display in green if the required quantity is fully assigned. |
Cost | The cost of all items in the actual column. Values in brackets are items on back order. |
Projected Remaining Cost |
This is the estimated material cost excluding the actual material costs to date. You can adjust this value manually |
You can also create