In the Details > Summary tab of the original job, select the Include: Variations and Include: Linked Variations check boxes to include variation values in your job breakdown table.
US only: If you use Simpro Premium in the United States, the term 'change order' is used instead of 'variation'. Learn more in About Change Order Costs.
In order to view content or perform actions referred to in this article you need to have the appropriate permissions enabled in your security group. Go to System > Setup > Security Groups and access your security group to update your permissions. The relevant security group tab and specific permissions for this article can be found here:
Actual costs on declined variations and variations awaiting approval are also included when this check box is selected. However, the billable price and estimated price of declined variations and those awaiting approval are not included in the Breakdown table.